‘A’ alone can do some work in 12 days. ‘B’ and ‘C’ together can do the same work in 6 days. If ‘B’ is half as efficient as ‘A’, then find the time taken by ‘C’ to complete the work alone.

A 5 days
B 7 days
C 9 days
D 8 days
E None of these