Let the total work be 12 units. {LCM (12 and 6)} So, efficiency of ‘A’ = (12/12) = 1 units/day So, efficiency of ‘B’ = (1/2) = 0.5 unit/day Efficiency of ‘B’ and ‘C’ together = (12/6) = 2 units/day So, efficiency of ‘C’ = 2 – 0.5 = 1.5 units/day So, time taken by ‘C’ to finish the work alone = (12/1.5) = 8 days