Question
βAβ alone can do some work in 12 days. βBβ and
βCβ together can do the same work in 6 days. If βBβ is half as efficient as βAβ, then find the time taken by βCβ to complete the work alone.Solution
Let the total work be 12 units. {LCM (12 and 6)} So, efficiency of βAβ = (12/12) = 1 units/day So, efficiency of βBβ = (1/2) = 0.5 unit/day Efficiency of βBβ and βCβ together = (12/6) = 2 units/day So, efficiency of βCβ = 2 β 0.5 = 1.5 units/day So, time taken by βCβ to finish the work alone = (12/1.5) = 8 days
A can complete a work in 18 days and B can complete the same work in 24 days. They work together for 6 days, after which A leaves. In how many more days...
Ram and Shyam can complete a piece of work together in 15 days. If Shyam is 50% more efficient than Ram, find how long Shyam alon...
The ratio of time taken by P, Q and R to complete work alone is 4:5:2 respectively. If all three together complete the work in 8 days, then find in how ...
A and B together can do a piece of work in 30 days, B and C together can do it in 20 days. A starts the work and works on it for 5 days, then B takes it...
28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more wo...
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
Aaru Swati and Rajni can finish a work in 4 days if they work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will ...
βAβ is 80% more efficient than βBβ. βAβ and βBβ work together for 5 days after which βAβ is replaced by βCβ. βBβ and βCβ...
A and B together can complete a task in 12 days, while B and C together can complete the same task in 15 days. A and C together take 20 days to finish i...
A and B can complete a work together in 36 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed ...