Question
5 girls can do a piece of work in 9 days, 4 boys can do
the same piece of work in 8 days, 6 men do the same piece of work in 2 days and 4 women can do the same piece of work in 4 days. Who is least efficient?Solution
5 girls can do a piece of work = 9 days 1 girl can do a piece of work = 9 × 5 = 45 days. 4 boys can do a piece of work = 8 days 1 boy can do a piece of work = 4 × 8 = 32 days. 6 men can do a piece of work = 2 days 1 men can do a piece of work = 6 × 2 = 12 days. 4 women can do a piece of work = 4 days 1 woman can do a piece of work = 4 × 4 = 16 days. Hence, girls are least efficient.
Which of the following countries finished at second place in Uber cup 2022?
What is the main objective of the Memorandum of Understanding (MoU) signed between RBI and Bank Indonesia regarding local currencies?
Ratan Tata was awarded the PV Narasimha Rao Memorial Award for his contributions in which field?
TOPS is a flagship program of the Ministry of Youth Affairs and Sports which is an attempt to provide assistance to India’s top athletes. What is the ...
According to IMF, what is India’s revised GDP growth forecast for 2025?
Padma Bhushan awardee Kumudini Lakhia is renowned for which of the following dance forms?
What is the significance of the recently discovered dinosaur Fujianvenator prodigiosus in the context of avian evolution?
Which Akashvani show won Best Produced Audio Streaming Programme (Health and Fitness)?
What subsidy percentage is the government planning to offer for goods transport on inland waterways?
What was the penalty imposed on the Amod Nagric Co-operative Bank for KYC violations?