Question
A and B individually can complete the work in 28 days and 42 days respectively. If the time taken by C alone to complete the work is 1.25 times the time taken by A and B together to complete the work, find the time taken by C to complete the work while working alone.
More Time and work Questions
- Worker ‘P’ can finish a task in 54 days, which is 18 days quicker than worker ‘Q’. If they take turns daily starting with ‘P’, find the total time (in days...
- 'X' can complete 75% of a work in 15 days, whereas 'Y' can complete 25% of the same work in 10 days. They both started working together, but 'Y' left the j...
- Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
- 'G', 'H', and 'I', working together, can finish a task in 6 days. 'G' and 'H' can do it in 7.2 days, and 'H' and 'I' in 9 days. How long would it take for ...
- Asmita and Bhanu working together can complete the task in ____ days, and the efficiency of Sam is 50% more than that of Asmita. Bhanu alone can complete o...
- 25 laborers working 7 hours daily can finish a road in 16 days. If 35 laborers work 8 hours each day, how many days are needed?
- A and B together, B and C together and A and C together can complete a piece of work in 11 days, 20 days and 12 days respectively. Find the ratio of the ef...
- ‘X’ and ‘Y’ together can complete a work in 16 days, while ‘Y’ and ‘Z’ together can complete the work in 10 days. If ‘Y’ takes 20 days to complete the work...
- Aman, Arun and Abraham can complete a work in 12, 20 and 24 days respectively. They all start working together. Aman left the work 1 day before its complet...
- Ishan alone can do a certain piece of work in 'w' days and Bhanumati can do it in '2w' days (w is a positive integer). Both together can do the work in 'x'...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)