Question
A can finish a piece of work in 12 days and B can finish it in 18 days. They work together for 3 days and then B leaves. In how many more days will A alone finish the remaining work?
More Time and work Questions
- A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C tog...
- (x + 9) laborers complete 45% of a task in 12 days working 5 hours/day. The rest is done by (x + 4) laborers in 18 days working 5 hours/day. Find x.
- 20 women can complete a task in 10 days by working 6 hours per day. How many women are required to complete the task in 5 days by working 8 hours per day?
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...
- A can complete a work in 30 days and B in 20 days. They work together for 6 days. The remaining work is completed by C alone in 10 days. In how many days c...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 6 ti...
- Ankit can complete a task in 16 days, while Bina alone can complete the same task in 24 days. Ankit starts the work alone and continues for 6 days. Then, B...
- If 'A' needs 24 more days to complete a certain task working alone compared to when 'A' and 'B' work together, and 'A' is 50% more efficient than 'B', what...
- Ravi and Sanjay take 54 days to build a fence. When they work along with Rahul, the work gets done in 36 days. Find the time Rahul alone would take to buil...
- 4 girls working together for 1 day complete the same amount of work as 6 men working together for 1 day. The efficiency of 1 man is 50% of the efficiency o...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)