Question
John, Emily, and Michael can each complete a task in 15
days, 20 days, and 18 days, respectively. They decide to work on the task alternately, starting with John, followed by Emily, and then Michael for 15 days. The remaining work is handled by Michael alone. Calculate the total time taken to complete the entire task using this alternating work pattern.Solution
ATQ, Let the total work = 180 units {LCM of 15, 20 and 18} Efficiency of ‘John’ = (180/15) = 12 units/day Efficiency of ‘Emily’ = (180/20) = 9 units/day Efficiency of ‘Michael’ = (180/18) = 10 units/day So, work completed in 3 days = (12 + 9 + 10) = 31 units Work completed in 15 days = 31 × 5 = 155 units Time taken by ‘C’ to complete the remaining work = (180 – 155)/10 = 2.5 days Therefore, total time taken = 15 + 2.5 = 17.5 days
- A shopkeeper makes a profit of 25% by selling an item for Rs. 500. What should be the selling price to make a profit of 40%?
A retailer buys two items at the same cost price. He sells one at a 25% profit and the other at a 20% loss. If the overall profit is rupees 15, find the...
If x = 3tan t, y = 3sec t, then the value of d2y/dx2 at t = π/4​ is:
The average of 26 numbers is 45. If 4 is added to each number, then the new average will be:
If tan(π/4 + θ) = 3, find tan(2θ):
A milkman initially prepared a mixture of milk and water in the ratio of 11:3. Later, he replaced half of the mixture with 30 liters of water, resulting...
A cyclist rides at a constant speed of 12 miles per hour for the first half of a journey. For the second half, the cyclist increases the speed to 18 mil...
Quantity I: ‘X’ – For a number greater than one, the difference between the number and its reciprocal is equal to 40% of t...