Question
John, Emily, and Michael can each complete a task in 15
days, 20 days, and 18 days, respectively. They decide to work on the task alternately, starting with John, followed by Emily, and then Michael for 15 days. The remaining work is handled by Michael alone. Calculate the total time taken to complete the entire task using this alternating work pattern.Solution
ATQ, Let the total work = 180 units {LCM of 15, 20 and 18} Efficiency of ‘John’ = (180/15) = 12 units/day Efficiency of ‘Emily’ = (180/20) = 9 units/day Efficiency of ‘Michael’ = (180/18) = 10 units/day So, work completed in 3 days = (12 + 9 + 10) = 31 units Work completed in 15 days = 31 × 5 = 155 units Time taken by ‘C’ to complete the remaining work = (180 – 155)/10 = 2.5 days Therefore, total time taken = 15 + 2.5 = 17.5 days
Find the correct word.
Select the most appropriate meaning of the given idiom.Â
Take exception
Tepid (A) / timid (B) economic growth hasn’t helped, and states have had to resort to higher market borrowings.
The Centre has been short-chan...
Ubiquitous
ENRAVISH - The classical dancer gave such a performance that enravished the audience.Â
Select the most appropriate option to replace the bold word in the given Sentence.
What are a few factors that contributes to water pollution?
Select the most appropriate meaning of the given idiom.
Go the extra mile
The association has welcomed (A) the decision to administer (B) booster dose to senior citizens and community workers and has called for stocking (C) u...
During the pandemic, especially (A) in 2020, the station officer earmarked (B) specific timing for each complainant (C) to address their griefances (D) ...
Any prolonged (A) / impersonating (B) attempt to isolate the country would not only have economic consequences but also complicate the fight against the...