Question
A can do a piece of work in 12 days and B can do it in 18 days. In how many days will they complete the work together?
More Time and work Questions
- A and B alone can complete a work in 20 and 30 days, respectively. 50% of the work is completed by C in 5x days, and the remaining work is completed by A a...
- A group of 3 men and 5 women can finish a task in 12 days, while another group of 5 men and 3 women can complete the same task in 9 days. If one man and on...
- X, Y and Z can do a piece of work in 90 days, 40 days and 120 days respectively. If they all work together alternatively starting with X, Y than Z respecti...
- 25 men can complete a piece of work in 30 days. ‘x’ men started the work and after 24 days 60 more men joined them so that whole work was finished in the d...
- 'B' alone can complete a work in 16 days while 'A' and 'B' together can complete the same work in 8 days. 'A' alone started the work and left after 4 days ...
- The time taken by ‘A’ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time required by...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work &lsqu...
- 'A' and 'B' alone can complete a work in 14 days and 21 days, respectively. Find the time taken by them to complete the work if they work on alternate days...
- A alone can finish the work in 10days and B alone can finish the same work in 15 days. All A, B and C together take 5 days to finish the work. Find the tim...
- Aman is twice as efficient as Suman. Both of them began working together, but Aman stopped after 12 days. Suman then finished the remaining work in 4 days....
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt