     A can do a piece of work in 12 days and B can do it in

    18 days. In how many days will they complete the work together?
    A 7(1/2) days Correct Answer Incorrect Answer
    B 7(1/5) days Correct Answer Incorrect Answer
    C 12 days Correct Answer Incorrect Answer
    D 8 days Correct Answer Incorrect Answer

    Solution

    ATQ, A's 1 day work = 1/12 B's 1 day work = 1/18 Together: 1/12 + 1/18 = 3/36 + 2/36 = 5/36 Time taken = 36/5 days = 7 (1/5) days Answer: B. 7 (1/5) days