Question
Two workers, Ravi and Suresh, started a project together. They worked together for the first 5 days, but only 25% of the project was completed. So, Ravi and Suresh increased their respective efficiencies by 50% each, such that the work was completed on time. If they had not increased their respective efficiencies, then the work would have been delayed by how many days?
More Time and work Questions
- Saurabh can complete a piece of work in 20 days. He worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both of them had done t...
- C is 50% more efficient than D and can complete a task in 18 days. C and D work together for 6 days, after which D leaves. In how many more days will C fin...
- 18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the task...
- 25 men can finish a work in 8 days by working 9 hours a day. How many more men are needed to finish the work in 10 days by working 6 hours a day?
- ‘A’ alone can do some work in 12 days. ‘B’ and ‘C’ together can do the same work in 6 days. If ‘B’ is half as efficient as ‘A’, then find the time taken by...
- Ishan alone can do a certain piece of work in 'w' days and Bhanumati can do it in '2w' days (w is a positive integer). Both together can do the work in 'x'...
- 25 employees working 9 hours a day take 20 days to complete a project. How many employees working for 8 hours a day are needed to complete twice the given ...
- Time taken by A and B together to complete a work is 1 day less than the time taken by B alone to complete the same work. With his half efficiency B can co...
- A buffalo alone can plough field ‘A’ in 20 days. A Bull alone can plough the field ‘A’ in 32 days. Find the number of days taken by 2 bulls and 2 buffalo t...
- Karan is five times as efficient as Varun and twice as efficient as Arjun. If Varun takes 30 days to finish some work, then find the time taken by Karan an...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)