      Question

      A can complete a job in 12 days, B in 18 days. They work

      together for 6 days, then A leaves. How many more days will B take to finish the remaining work?
      A 7 days Correct Answer Incorrect Answer
      B 4 days Correct Answer Incorrect Answer
      C 3 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer

      Solution

      ATQ, A’s 1 day work = 1/12, B’s = 1/18 Together for 6 days: Work done = 6 × (1/12 + 1/18) = 6 × (5/36) = 5/6 Remaining = 1 - 5/6 = 1/6 B alone: Time = (1/6) ÷ (1/18) = 3 days