A can complete a work in 12 days, and B can complete the
same work in 18 days. How many days will they take to complete the work if they work together?Solution
Aβs rate of work = 1/12 Bβs rate of work = 1/18 Together, their rate of work = 1/12 + 1/18 = (3 + 2) / 36 = 5/36 So, the time taken to complete the work together = 36/5 = 7.2 days Correct option: b
βAβ and βBβ started a business by investing Rs. 9000 and Rs. 11000, respectively. 12 months later, βCβ joined the business by investing Rs. ...
Aman, Bhanu, and Chinky commenced a business with initial investments in the ratio 5:7:8, respectively. After one year, they made additional investments...
D and E invested Rs.24000 and Rs.18000 in a business. After 4 months F joined with Rs.22000. After 3 months of Fβs joining, D withdrew Rs.4000 and E w...
'Pawan' and 'Qureshi' invested 9,000 and 12,000 rupees, respectively, to establish their businesses. 6 months later, 'Pawan' invests 'b' more money, and...
Three persons A, B and C invested different amounts in a business, which are in A.P. The amount invested by B is Rs. 2000 more than that of A. C investe...
βAβ and βBβ started a business by investing Rs. 4000 and Rs. 8000, respectively. 8 months later, βCβ joined them with an investment equal to...
"A" and "B" initiated a partnership with investments in the proportion of 3:4. After four months, "C" entered the partnership by contributing Rs. 75,000...
βAβ and βBβ started a business by investing Rs. βaβ and Rs. βa + 250β, respectively. If 12 months later the ratio of profit shares of οΏ½...
If the ratio of time periods of investment of A and B is 5:6, profit at the end of the year is Rs.100000 and Aβs share in it is Rs.25000, then what is...
Akshay and Akhil invest in a business in the ratio 4:1. If 10% of the total profit goes to charity and Akshay's share is Rs. 864.Then find the total pro...