Question
Anurag can finish a task in 60 days, while Bhuvan can
complete the same task in 80 days. Anurag begins working alone, and after 39 days, Bhuvan joins him. How many more days will Anurag and Bhuvan take together to complete the remaining work?Solution
ATQ;
Let the total amount of the work = 240 units (LCM of 60 and 80)
Anurag’s efficiency = 240/60 = 4 units per day
Bhuvan’s efficiency = 240/80 = 3 units per day
Amount of the work done by A in 39 days = 39 × 4 = 156 units
Remaining amount of the work = 240 – 156 = 84 units
Remaining amount of the work done by Anurag and Bhuvan together = 84/7 = 12 days
Which of the following is the justification that aligns text on both margins of a document in Word?
If both the equations I and II given below are added, then find the product of roots of newly formed equation.
I: 3x2 + 9x + 5
...
The ratio between the speed of a bus and train is 15:27 respectively. Also, a car covered a distance of 720 km in 9 hours. The speed of the bus is three...
Two places X and Y are 450 km apart. A truck leaves place X from place Y and at the same time another truck leaves place Y to X. Both the men meet 9 hou...
If x and y are the roots of x2 + x + 3 = 0, then (x11 + y11)/(x-11 + y-11) is equal to:
The main folder on a storage device is known as
If the product of roots of equation x2 - 3(2p+4)x + (p2 - 24p + 145) = 0 is unity, then 'p' can take the values as
A train of length 260 m crosses another train of length 120 m running is opposite direction in 5 sec. If speed of longer train is 90 km/h, then in what ...
The question consists of four statements: I, II, III and IV given below it. You have to decide whether the data given in which of the following statemen...
A and B are the roots of equation x2 - 13x + k = 0. If A - B = 5, what is the value of k?