Question
Anurag can finish a task in 60 days, while Bhuvan can
complete the same task in 80 days. Anurag begins working alone, and after 39 days, Bhuvan joins him. How many more days will Anurag and Bhuvan take together to complete the remaining work?Solution
ATQ;
Let the total amount of the work = 240 units (LCM of 60 and 80)
Anurag’s efficiency = 240/60 = 4 units per day
Bhuvan’s efficiency = 240/80 = 3 units per day
Amount of the work done by A in 39 days = 39 × 4 = 156 units
Remaining amount of the work = 240 – 156 = 84 units
Remaining amount of the work done by Anurag and Bhuvan together = 84/7 = 12 days
According to the data released by the National Statistical Office (NSO), Consumer Price Index-based inflation rate rose to a three-month high at ___.
What is the theme of World Standards Day 2025, celebrated on October 14?Â
Which of the following NBFCs was ordered by RBI to stop lending due to regulatory violations recently (Oct 2024)?
Which ministry hosted the 'Run for Sun' Marathon in New Delhi to celebrate International Sun Day?
The index provider arm of the National Stock Exchange has announced five additions and deletions each to the Nifty Next 50 Index.Apart from the addition...
- Which organization implements the National Agriculture Market (NAM) platform?
In order to strengthen the nursing workforce in the country, the Cabinet Committee on Economic Affairs, has approved the establishment of _______ new nu...
Consider the following in regards to ADB :
1) It has granted a US$ 250 million loan for Delhi-Meerut Regional Rapid Transit System (RRTS).
What is the Assets under Management (AuM) reported by SBI Life Insurance as per the latest available data?
Which of the following best describes the function of peroxisomes in eukaryotic cells?