      Question

      Ashish and Anil can do a piece of work in 20 days and 28

      days respectively. Ashish completed 75% of the work. Find the time taken by Anil to complete the remaining work.
      A 15 days Correct Answer Incorrect Answer
      B 18 days Correct Answer Incorrect Answer
      C 11 days Correct Answer Incorrect Answer
      D 7 days Correct Answer Incorrect Answer

      Solution

      Let the total work be (LCM of 20 and 28) = 140 units Efficiency of Anil = 140/28 = 5 units/day Remaining work = 140 x 0.25 = 35 units Time taken by Anil to complete the remaining work = 35/5 = 7 days