Question
Ashish and Anil can do a piece of work in 20 days and 28
days respectively. Ashish completed 75% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 20 and 28) = 140 units Efficiency of Anil = 140/28 = 5 units/day Remaining work = 140 x 0.25 = 35 units Time taken by Anil to complete the remaining work = 35/5 = 7 days
Which is the Fastest train in India?
Which railway station has received the first green Platinum rating in 2019?
In the Railway Budget of 2016, three dedicated freight corridors were announced. Which of the following is one of them?
Who among the following is the first female locopilot (train driver) of the Indian Railways in India?
What is the meaning of yellow light in railway?
Which institution released a report titled ‘Derailment in Indian Railways’?
Where is the Rail Wheel Plant located?
Shatabdi Express train was started in ________.
What did the first functional railway that was started in Madras transport?
Which Committee recommended that all Indian Railways should be managed in India?