      Question

      A and B can complete a task together in 12 days, while B

      alone takes 24 days to finish it. A began working alone and left after β€˜x’ days, after which B completed the remaining work in 18 days. Determine the percentage of the total work completed by A.
      A 25% Correct Answer Incorrect Answer
      B 15% Correct Answer Incorrect Answer
      C 20% Correct Answer Incorrect Answer
      D 40% Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let total amount of work be 16 unitsEfficiency of (A + B) = 16/8 = 2 units/dayEfficiency of β€˜B’ = 16/16 = 1 unit/dayAmount of work done by β€˜B’ = 12 Γ— 1 = 12 unitsPercentage of work done by β€˜A’ = {(16 – 12)/16} Γ— 100 = 25%