Question
‘A’ alone can complete a work in 12 days. ‘B’
alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 6 days, then the remaining work can be completed by ‘A’ alone in how many days?Solution
Let the total amount of work = 60 units {LCM of 12 and 20} Then, efficiency of ‘A’ = 60/12 = 5 units/day Efficiency of ‘B’ = 60/20 = 3 units/day Combined efficiency of ‘A’ and ‘B’ = 5 + 3 = 8 units/day Work completed by ‘A’ and ‘B’ together in 6 days = 6 × 8 = 48 units Remaining work = 60 – 48 = 12 units Time taken by ‘A’ alone to complete the remaining work = 12/5 = 2.4 days
What percentage of India’s population was covered under social security in 2025 according to ILO recognition?
Which city recently saw the inauguration of Standard Chartered’s second international banking center for global Indians?
Indian musicians Ricky Kej and Anoushka Shankar have been nominated for which prestigious awards in 2025?
India signed an MoU with Fiji for the design, construction, and operation of what type of hospital?
________ has set up a specialized branch for start-ups to provide end-to-end support at every stage of their journey, starting from the formation of the...
Recently Yoon Suk-Yeol was sworn in as the new President of Which country?
Which financial services provider launched the advanced ‘Push Provisioning’ platform?              Â
...In which city will the FIFA Club World Cup 2023 be organized?
Which of the following is not in the most powerful woman from India in the Forbes list 2023?
Which of the following bank adjudged as best performing bank in Self Help Group (SHG) Linkage by Deendayal Antyodaya Yojana – National Rural Livel...