Question
βAβ alone can complete a work in 12 days. βBβ
alone can complete the same work in 20 days. If βAβ and βBβ work together for 6 days, then the remaining work can be completed by βAβ alone in how many days?Solution
Let the total amount of work = 60 units {LCM of 12 and 20} Then, efficiency of βAβ = 60/12 = 5 units/day Efficiency of βBβ = 60/20 = 3 units/day Combined efficiency of βAβ and βBβ = 5 + 3 = 8 units/day Work completed by βAβ and βBβ together in 6 days = 6 Γ 8 = 48 units Remaining work = 60 β 48 = 12 units Time taken by βAβ alone to complete the remaining work = 12/5 = 2.4 days
As per FSSA in packaging requirements for fruit and vegetable products, juices and pulps may be packed in the following type of container, when sulphited
Which of the following sentence is INCORRECT with respect to storage temperature?
Sanitization is a process by which
a.Β Β Β Β Β Β The microbial load on objects is reduced
b.Β Β Β Β Β Objects are made steri...
Tomato fruits for canning are harvested at:
The time required to kill 90% of the microorganisms in a sample at a specific temperature is the
a)Β Β Β Β Β Β thermal death point
b...
Foods high in trans fats are
The water activity is measured on a scale of range
In which of the following method, heating is due to electrical resistance of a food
A rich dietary source of cholesterol is:
Which of these are glass container closure types?
Options:
1. Lug caps
2. Roll on caps
3. Continuous thread closures
4. T-top closures