Question

‘A’ alone can complete a work in 20 days. ‘B’ alone can complete the same work in 25 days. If ‘A’ and ‘B’ work together for 7 days, then the remaining work can be completed by ‘A’ alone in how many days?

A 5.4 days
B 6.4 days
C 7.4 days
D 8.4 days