πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      Mike and Jenny alone can complete a task in 24 days and

      40 days respectively. They aim to finish the work in 'd' days. What percentage increase in Jenny's efficiency is required for them to finish the work in 'd/2' days?(Can calculate approx. value)
      A 267% Correct Answer Incorrect Answer
      B 150% Correct Answer Incorrect Answer
      C 200% Correct Answer Incorrect Answer
      D 295% Correct Answer Incorrect Answer
      E none of these Correct Answer Incorrect Answer

      Solution

      ATQ, Total work = LCM of 24 and 40 = 120 units Efficiency of Mike = 120 / 24 = 5 units/day Efficiency of Jenny = 120 / 40 = 3 units/day Combined efficiency = 5 + 3 = 8 units/day Original time (d) = 120 / 8 = 15 days Required time (d/2) = 7.5 days Required total efficiency = 120 / 7.5 = 16 units/day Increase needed for Jenny = 16 - 5 = 11 units/day Percentage increase = ((11 - 3) / 3) Γ— 100 = 266.67% or 267%

      Practice Next

      Relevant for Exams:

      ask-question