Question
Efficiencies of workers A, B, and C are in the ratio 5:7:8
respectively. If B and C can do the work in 9 days, then in how many days can A and B finish the work together?Solution
ATQ,
Let efficiencies of A, B, and C be 5x, 7x, and 8x units/day respectively.
Total work = (7x + 8x) Γ 9 = 135x units
Required time = 135x Γ· (5x + 7x) = 135x Γ· 12x = 11.25 days
If p: q =1:3, q: r =2:1, r: s = 1:2, s: t =3:1 and t: u =1:4 then value of (p q r/s t u)3 =?
If the ratio of number of boys and girls present in the playground is 5:4. 10 boys left the playground, leaving total number of girls same as the boys p...
Total population of city P and Q is 3150 and 3640 respectively. If the ratio of number of males to females in city is P and Q is 5:4 and 4:3 respectivel...
If A:B = 7:6 and B:C = 12:15 respectively, then find the value of (A + C) :(A + B) .
A right triangle ABC with sides 5 cm ,12cm and 13cm is revolved about the side 12 cm. What is the volume of the solid so obtained?
A seller sold three types of fruits i.e. apples, bananas, and oranges. The number of apples sold is 30% of the total number of fruits sold, and the rati...
- If βAβ, βBβ and βCβ are in proportion in the given order while βAβ = 12 and βBβ = 36, then find the value of βCβ.
The ratio of the two numbers is 4:7. 110% of the first number is equal to the 80% of the second number. Find the sum of both the numbers.
What is the mean proportion between 9 and 36?
Rs 2106 was divided among Anil, Bhanu and Charan in the ratio of 13:10:16 respectively. Find the amount received by Anil and Bhanu together.