Efficiencies of workers A, B, and C are in the ratio 5:7:8
respectively. If B and C can do the work in 9 days, then in how many days can A and B finish the work together?Solution
ATQ,
Let efficiencies of A, B, and C be 5x, 7x, and 8x units/day respectively.
Total work = (7x + 8x) × 9 = 135x units
Required time = 135x ÷ (5x + 7x) = 135x ÷ 12x = 11.25 days
- The area of the base of a rectangular water tank is 450 m² and the volume of water contained in it is 15750 m³. Find the height of the water level in the...
The volume and height of a cylinder are 7986 cm3 and 21 cm. Find the radius of the cylinder.
The length of the rectangle is triple its breadth. If the perimeter of the rectangle is 120 m, then find the area (in m 2) of the rectangle.
A solid cone and a solid hemisphere have the same radius and height. If the volume of the cone is 540 cm³, find the volume of the hemisphere.
The sum of the perimeters of a square and a rectangle is 120 metres. If the sum of the length and breadth of the rectangle is 30 m, then find the area o...
The circumference of a circle is equal to the perimeter of a rectangle whose length and breadth are in ratio 5:3, respectively. If the area of the recta...
If the diameter of the cylinder is 14 cm and height of the cylinder is 2cm. Find the sum of the curved surface are and total surface area?
Find out the diameter of the incircle of a given triangle with a semi-perimeter of 24 cm and an area of 72 cm².
A square playground measure 1127.6164 meter2. If a man walks (49/20) m a minute, the time taken by him to walk one round around is approximat...
The volume of water measured on a rectangular field 400m `xx` 200m is 8000 . Find the depth (amount) of rain that has fallen.