Question
A can complete a work in 12 days, while B can complete it in 15 days. How many days will they take to finish the work together?
More Quant Miscellaneous Questions
- 'P' invested a certain amount at 21% per annum simple interest for 2 years. If he had instead invested the same amount at 20% per annum compound interest, ...
- f A and B are independent events with P(A) = 0.6, P(B) = 0.5, then P(A υ B)) = ?
- An item priced at Rs. 1,500 has a markup of 36% on its cost price and is sold with two successive discounts: the first being 15% and the second being Rs. 1...
- A 36-litre mixture of milk and honey contains them in the ratio 5 : 4. How much honey should be added to the mixture so that the ratio of milk to honey bec...
- OCR stands for __________
- A container contains a mixture of three liquids A, B, and C in the ratio 4:3:2. If 18 liters of this mixture is removed and replaced with 9 liters of liqui...
- If a = 0.121212… (repeating) and b = √5, state whether each is rational or irrational.
- 'R' invested Rs. 24,000 in SIP 'A' with a compound interest rate of 20% per annum compounded annually, and Rs. 18,600 in SIP 'B' with a simple interest rat...
- A seller sells an item for Rs. 225.50 and incurs a loss of 18%. At what price should the item be sold in order to achieve a profit of 12%?
- From a point 30 m away from the base of a building, the angle of elevation to the top of the building is 60°. Find the height of the building.
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)