Question
A and B individually can complete the work in 20 days and 30 days respectively. If the time taken by C alone to complete the work is 1.25 times the time taken by A and B together to complete the work, find the time taken by C to complete the work while working alone.
More Time and work Questions
- Ajay started a work and left working after 8 days. Vijay finished the remaining work in next 36 days. Had Ajay left the work after working for 12 days then...
- A certain amount earns Rs. 2,400 as simple interest in 4 years at 12% per annum. If the same amount is invested at 8% per annum for 2 years, what will be t...
- 5 Pandavas can do a work in 18 days, 4 Kauravas can do the same work in 30 days. Now, in how many total days the total work be finished if 1 Panadva and 1 ...
- ‘A’ and ‘B’ can complete a certain work in 12 days and 24 days, respectively. They started working together and worked till completion of the work for whic...
- A alone can complete a piece of work in 15 days, while B alone can complete it in 20 days. They start the work together, and after some days A leaves. B co...
- A can copy 80 pages in 20 hours, A and B together can copy 135 pages in 27 hours. Then Y can copy 20 pages in
- Pawan can finish a task in 28 days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started working together but stopped ...
- 40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are nee...
- Aisha and Neel can complete a job alone in 66 days and 99 days respectively. Working together, they earn a total wage of Rs. 11,550. How much does Aisha re...
- ‘A’ and ‘B’ can complete a certain work in 13 days and 26 days, respectively. They started working together and worked till completion of the work for whic...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt