Question
Sam alone can complete a work in 60 days. Arun is three times as efficient as Sam. Find the percentage of work completed by Sam and Arun together in 15 days.
More Time and work Questions
- 15 men working 9 hours daily can finish a task in 36 days, while 18 women working 6 hours a day complete the same task in 72 days. How many days will 6 men...
- Alex and John can finish a translation project alone in ‘p’ and ‘q’ days, respectively. The time taken by Alex to complete the project is 50% of the time t...
- 168 unit of work can be completed by P alone in 28 days. P started working alone and joined by Q after 10 days such that they completed the remaining work ...
- A, B and C are hired at Rs 1050 to do a piece of work. A and B together complete 19/23 part of the work. And B and C together complete 8/23 of the work. Th...
- A and B can complete a task together in 18 days, while B alone takes 36 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- X men can complete the piece of work in 45 days and (X + 46) men can complete the same work in 23 days less than that of days taken by X men. Find the valu...
- A can do a work in 45 days and the same the work is done in 15 days by A and B together, then in how many days B can complete the 20% of work?
- A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
- The time taken by ‘A’ to build a wall alone is 40% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
- A is capable of finishing a task in 60 days. B requires 40% more time than A to finish the same task. How many days will A and B need to complete 80% of th...