Question
Sam alone can complete a work in 60 days. Arun is three
times as efficient as Sam. Find the percentage of work completed by Sam and Arun together in 15 days.Solution
ATQ,
Let the efficiency of Sam = x units/day
Total work = 60x units
Efficiency of Arun = x × 3 = 3x units/day
Work done by Sam and Arun together in 15 days = (x + 3x) × 15 = 60x units
Percentage of work done = (60x / 60x) × 100 = 100%
Which test is commonly used to detect the presence of starch in milk adulteration?
Read the statements and then find the correct answer.
i.                    Striated muscles are voluntary muscles.
i...
Curly toe paralysis presents as inward curling of the toes on the chicken's feet, which impairs their ability to walk. Curly toe paralysis is caused by ...
Fruit cracking problem in pomegranate is due to the deficiency of which elements?
The biggest breed of Indian goat is –
Pregnant animals are transferred to a calving pen 2 to 3 weeks before the expected date of calving. Number of calving pen required is what % of the numb...
Highest milk yielding cow breed
Strip Cup test is used for identifying which disease ?
Hen and Chicken disease in grapes is caused due the deficiency of ___
Which part of ruminant’s stomach is called its true stomach?Â