      Question

      A group of 21 boys, each working

      6 hours a day, complete a school project in 15 days. How many days will it take for 18 boys, working 5 hours daily, to finish the same project?
      A 21 Correct Answer Incorrect Answer
      B 11 Correct Answer Incorrect Answer
      C 19 Correct Answer Incorrect Answer
      D 32 Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the required time be 'd' days. So, 21 × 6 × 15 = 18 × d × 5 Or, 1,890 = 90 × d Or, 'd' = 21 