Question
In an office, an employee plans to do a work in 12 days
with 4 laptops. But after 4 days, he found that only 40% of the work is done with the laptops working for 4 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?Solution
Laptops do 40% of the work in 4 days, or 4 × 4 = 16 hours. So the rest of the (i.e., 60% of the work) can be done in, => (60 × 16)/40 = 24 hours This 24 hours of work has to be done in the remaining (12 – 4) = 8 days. Laptops have to work (24/8) = 3 hours a day to complete the work in the planned time.
Find the missing number.
.Â
...Choose the correct alternative that will complete the given number series. 2, 9, 28, 65, ?, 217
In the following question, select the missing number from the given alternatives.
45, 15, 60, 75, 135, ?
Study the given pattern carefully and select the number that can replace the question mark [?] in it.
Study the given pattern carefully and select the number that can replace the question mark [?] in it.
First row: 6, 5, 191
Second row: 9, ...
Select the number that can replace the question mark (?) in the following series.Â
Select the number from the given option that can replace the question mark (?) in the following series:
32, 16, 24, 60, ?, 945
Find the missing term :
...
Select the missing number from the given responses.

Find the missing term in the given series:
4      3.5      ?           22.875               ...