A can do a piece of work in 12 days, while B
alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?Solution
Work done by A and B in 6 days = (1/12 + 1/18) × 6 = 5/6 Work remaining = 1 - 5/6 = 1/6 ∴ C alone can do the work in 6 × 4= 24 days Ratio of their share work = 6/12 : 6/18 : 4/24 = 3:2:1 Share of A’s wages = 3/6 × 720 = Rs. 360 Share of B’s wages = 2/6 × 720 = Rs. 240 Share of C’s wages = 1/6 × 720 = Rs. 120
Within one year of incorporation, what should be the ratio of net owned funds to the deposits for Nidhi companies?
The air conditioners not working in the office is which of the following factors?
Shannon-Weaver’s original model of communication consist of _________ components.
Which of the following private sector bank has launched two new products – loan against deposits and dollar bonds – for non-resident Indians at its ...
Abnormal Gain is shown on the …….side of the Process A/c and the ………… side of Abnormal Gain A/c
Current Assets (at cost) Rs.24,00,000, Credit Sales Rs. 68,00,000, Cash Sales Rs.600,000, Sales Return Rs.2,00,000. What can be Current Assets Turnover ...
What is the insurance cover provided under the 'Pradhan Mantri Garib Kalyan Package: Insurance Scheme for Health Workers Fighting COVID-19'? Â
There can be a variety of budget. Name the budget which relates to a particular function of the business.
A startup company with a promising technology but limited operating history and no substantial assets is seeking funding to fuel its growth and developm...
What was the cumulative disbursement by IIFCL by the end of FY2023-24, as per the Annual Report of IIFCL 2023-24?