Question
A can do a piece of work in 12 days, while B
alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?Solution
Work done by A and B in 6 days = (1/12 + 1/18) × 6 = 5/6 Work remaining = 1 - 5/6 = 1/6 ∴ C alone can do the work in 6 × 4= 24 days Ratio of their share work = 6/12 : 6/18 : 4/24 = 3:2:1 Share of A’s wages = 3/6 × 720 = Rs. 360 Share of B’s wages = 2/6 × 720 = Rs. 240 Share of C’s wages = 1/6 × 720 = Rs. 120
In 2016, who partnered with ISRO to use space technology for 'predictive policing'?
Which of the following is a human factor responsible for soil erosion?
1. Deforestation
2. Run off water
3. Overgrazing
...What was India’s Direct Tax collection for the previous financial year (2023-24)?
As of January 2020, which of the following is NOT a Maharatna company?
What is the full form of TSX?
Which scientist suggested that the magnet must also exert an equal and opposite force on the current-carrying conductor?
Who won the 2024 International Booker Prize for "Perfection" (original title: "Vincenzo")?
The 2016 World Economic Forum Annual Meeting took place in-
The ‘Pradhan Mantri Jan Arogya Yojana’ (‘PM-JAY’) scheme of the government is associated with which of the following Directive Principles of Sta...
For the 18th Lok Sabha elections, which district in Haryana featured in special Pink, Green, Youth, and PWD booths?