span >A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?
More Time and work Questions
- A can complete a work in 24 days, B in 36 days and C in 48 days. All three start working together. After 4 days, A leaves the work. B and C continue the wo...
- Vijay can do a piece of work in 10 days and Sanjay can do the same work in 15 days. If Vijay works for 4 days and got Rs. 1680, and the remaining work will...
- A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extr...
- A team of 32 men and 28 women can complete a task in 60 days. When an additional eight men join the team, they are able to finish (4/5) of the same task in...
- A and B together can complete a work in 15 days, while B and C together can complete the same work in 20 days. If A, B, and C together can complete the wor...
- 'Meera', 'Kiran', and 'Suman' together can complete a work in 30 days. 'Meera' and 'Kiran' together can complete the same work in 90 days. 'Suman' alone ca...
- ‘A’ alone can complete a piece of work in 30 days while ‘A’ and ‘B’ together can complete the same work in 20 days. ‘B’ started the work and after 4 days ‘...
- Ajay and Bheem collectively earned Rs.9,000 for completing a task, with Bheem's share being Rs.3,000. If Bheem can complete the work on his own in 48 days,...
- A and B can complete a task together in 10 days, while B alone takes 20 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- Manoj can complete a job in 10 days which Rakesh can do in 15 days. Rakesh can finish a task in 20 days which Suresh can complete in 25 days. In how many d...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)