Question
span >A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?
More Time and work Questions
- A buffalo alone can plough field ‘A’ in 30 days. A Bull alone can plough the field ‘A’ in 50 days. Find the number of days taken by 2 bulls and 1 buffalo t...
- Krishna can do a piece of work in 25 days. He alone worked at it for 10 days and then Balram completed alone the rest work in 20 days. In how many days, th...
- A can plough a field alone in 12 days and B alone can do it in 18 days. They work together for 4 days and then B alone finishes the remaining work. In how ...
- X can do a piece of work in 20 days. He worked at it for 4 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
- Virat can do a piece of work in 28 days and Sachin can do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will...
- A and B individually can complete the work in 32 days and 48 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 18 days. 'A' started the work alone and worked on...
- If 15 women or 18 men or 12 boys can do a piece of work in 18 days of 10 hours each, find how many boys assisted by 5 women and 6 men will finish the same ...
- A work can be completed by ‘A’ and ‘B’, alone in 15 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- Three workers, A, B, and C, can complete a task in 40 days, 72 days, and 45 days respectively. They start working together, but A leaves 20 days before the...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)