Question
'A' and 'B' can together complete a job in 15 days. If 'B' alone can finish 50% of the job in 20 days, how long would it take 'A' alone to complete the entire job?
More Time and work Questions
- A, B and C alone can complete a work in 18, 32 and 24 days respectively. All of them started working together but after 3 days from start A left the job an...
- P alone can finish a piece of work ‘M’ in 5 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 11 t...
- Pawan, Bittu, and Raju can individually complete a task in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops aft...
- 20 women can complete a task in 10 days by working 6 hours per day. How many women are required to complete the task in 5 days by working 8 hours per day?
- The amount of work completed by 24 men in 5 hours is equivalent to the work done by 21 women in 8 hours. A team of 33 men, working 6 hours daily, can finis...
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
- A and B individually can complete the work in 32 days and 48 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- ‘A’ and ‘B’ together can complete a work in 16 days, while ‘B’ and ‘C’ together can complete the work in 12...
- Aarif, Arun, and Abraham can do work in 12, 15, and 24 days, respectively. They all begin together. Aarif leaves the work 1 day, Arun 3 days and Abraham 4 ...
- If the efficiency ratio of A, B, and C is 7:9:11, and B and C together can finish a task in 10 days, then how much time will A and B need to complete it?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt