Question
'A' and 'B' can together complete a job in 15 days. If
'B' alone can finish 50% of the job in 20 days, how long would it take 'A' alone to complete the entire job?Solution
ATQ, Time taken by 'B' to complete the job alone = 20 × (100/45 ) = 40 days. Let the total work be 120 units. {LCM of 15 and 40}. Efficiency of 'A' and 'B' together = (120/15) =8 units/day. Efficiency of 'B' = (120/40) = 3 units/day. Efficiency of 'A' = 8−3 = 5 units/day. Time taken by 'A' to complete the work alone = (120/5) = 24 days.
Consider the following statements about Krishi 24/7:
1. It is the first-ever AI-powered solution for automated agricultural news monitoring
...How much financial assistance has REC Limited committed towards supporting the education of children in Siddharthnagar district, Uttar Pradesh?
The DRDO inaugurated the Quantum Technology Research Centre (QTRC) in which city of the country?
Which PSU bank was the first to eliminate the Average Monthly Balance (AMB) requirement completely?
For the success of Chandrayaan – 3 mission, who has been awarded with the International Astronautical Federation (IAF) World Space Award?
Consider the following statements regarding Pradhan Mantri Jan Dhan Yojana:
1.           All accounts under the scheme are provided w...
Which country has recently launched its first nuclear attack submarine?
Which article of the Indian Constitution deals with the Right to Constitutional Remedies?
By which year has the city of Dubai set goals to achieve Zero-Emissions public transportation?
Which place hosted the 18th edition of the India-Nepal joint military exercise Surya Kiran?