Question
βAβ can complete a work in 20 days and is 20% more
efficient than βBβ. βAβ and βBβ start the work together, but βAβ leaves after 10 days. The remaining work is completed by βBβ alone in βxβ days. Find the value of βxβ.Solution
ATQ, Time taken by βBβ to complete the work = 1.2 Γ 20 = 24 days Let the total work = 120 units Efficiency of βAβ = 120/20 = 6 units/day Efficiency of βBβ = 120/24 = 5 units/day Work completed by βAβ and βBβ in 10 days = (6 + 5) Γ 10 = 110 units Therefore, x = (120 β 110)/5 = 2 days
India’s first Gold ATM has been launched in which of the following cities?
Who was the first President of India from Uttar Pradesh?
What is the main goal of the Raising and Accelerating MSME Performance (RAMP) Scheme?
The GST Council meeting discussed tax relief on:
Who was the winner of Asian Kabaddi Championship under 23?
With reference to Virtual Digital Assets and Prevention of Money Laundering Act (PMLA) 2002 , consider the following statements:
1.Β Β Β VDA ser...
Which book was written by A.P.J. Abdul Kalam?
Dadri Mela is organised at which place?
Which of the statements given below is/are correct according to the Union Budget 2023-24:
1. PM VIKAS for centuries, traditional artisans and cra...
The Iron Pillar at Mehrauli in Delhi is believed to record the achievements of: