Question
‘A’ can complete a work in 20 days and is 20% more
efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 10 days. The remaining work is completed by ‘B’ alone in ‘x’ days. Find the value of ‘x’.Solution
ATQ, Time taken by ‘B’ to complete the work = 1.2 × 20 = 24 days Let the total work = 120 units Efficiency of ‘A’ = 120/20 = 6 units/day Efficiency of ‘B’ = 120/24 = 5 units/day Work completed by ‘A’ and ‘B’ in 10 days = (6 + 5) × 10 = 110 units Therefore, x = (120 – 110)/5 = 2 days
Which instrument can be used to detect water adulteration in milk?
Acid soil can be amended with the help of
Parturition in pigs is known as
Cryopreservation of seeds involves storage at:
Given below are two statements:
Statement I: Orobanche (Broomrape) is a total-root parasitic weed in rapeseed mustard.
Statement II: Strig...
Formation of deep cracks is the characteristics feature of:
नीचे दिए वाक्यों में से कुछ में त्रुटियाँ हैं और कुछ ठीक ह�...
Insects exhibiting complex social behavior with division of labor and cooperative brood care belong to which group?
Crop grown for sale to bring money immediately is termed as .................................?
Short term credit is usually for a period of ranging up to: