Question

‘A’ can complete a work in 15 days and is 50% more efficient than ‘B’. ‘A’ and ‘B’ start working together and ‘A’ leaves after 8 days. The rest of the work is completed by ‘B’ alone in ‘x’ days. Find the value of ‘x’.

A 2
B 3
C 1
E None of these