    Question

    β€˜A’ can complete a work in 15 days and is 50% more

    efficient than β€˜B’. β€˜A’ and β€˜B’ start working together and β€˜A’ leaves after 8 days. The rest of the work is completed by β€˜B’ alone in β€˜x’ days. Find the value of β€˜x’.
    A 2 Correct Answer Incorrect Answer
    B 3 Correct Answer Incorrect Answer
    C 1 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, Time taken by β€˜B’ to complete the work = 1.5 Γ— 15 = 22.5 days (round up to 23 days) Let the total work = 230 units Efficiency of β€˜A’ = 230/15 = 15.33 units/day (round to 15 units/day) Efficiency of β€˜B’ = 230/23 = 10 units/day Work completed by β€˜A’ and β€˜B’ in 8 days = (15 + 10) Γ— 8 = 200 units Therefore, x = (230 – 200)/10 = 3 days