Question
βAβ can complete a work in 15 days and is 50% more
efficient than βBβ. βAβ and βBβ start working together and βAβ leaves after 8 days. The rest of the work is completed by βBβ alone in βxβ days. Find the value of βxβ.Solution
ATQ, Time taken by βBβ to complete the work = 1.5 Γ 15 = 22.5 days (round up to 23 days) Let the total work = 230 units Efficiency of βAβ = 230/15 = 15.33 units/day (round to 15 units/day) Efficiency of βBβ = 230/23 = 10 units/day Work completed by βAβ and βBβ in 8 days = (15 + 10) Γ 8 = 200 units Therefore, x = (230 β 200)/10 = 3 days
Indore and Udaipur became the first Indian cities to receive Wetland City Accreditation under which international treaty?
Which cyclone formed over the Bay of Bengal in October 2024 and is expected to impact Odisha and West Bengal?
Who has been appointed as the first director of the Fund for Responding to Loss and Damage?
Nav Bharat Saaksharta Karyakram (New India Literacy Programme ) was held on 19.03.2023 across how many States and UTs in the country to assess the basi...
What is the inaugural edition of the 'Tarang Shakti 2024' multinational air exercise hosted by India?
Which of the following is NOT a mandatory document for enrollment in the Pradhan Mantri Jeevan Jyoti Bima Yojana (PMJJBY)?
- What is the new minimum investment amount in Social Stock Exchange ZCZP instruments as per SEBI's March 2025 update?
Which sector accounted for over half of the personal loan market according to RBIβs State of the Economy report?
What achievement was highlighted in the World Malaria Report 2024 regarding India?
- What is the targeted coverage of irrigation potential under the M-CADWM sub-scheme?