πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      β€˜A’ can complete a work in 18 days and is 10% more

      efficient than β€˜B’. β€˜A’ and β€˜B’ start the work together, but β€˜A’ leaves after 15 days. The remaining work is completed by β€˜B’ alone in β€˜x’ days. Find the value of β€˜x’.
      A 2 Correct Answer Incorrect Answer
      B 3 Correct Answer Incorrect Answer
      C 1 Correct Answer Incorrect Answer
      D 8 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Time taken by β€˜B’ to complete the work = 1.1 Γ— 18 = 19.8 days (round up to 20 days) Let the total work = 180 units Efficiency of β€˜A’ = 180/18 = 10 units/day Efficiency of β€˜B’ = 180/20 = 9 units/day Work completed by β€˜A’ and β€˜B’ in 15 days = (10 + 9) Γ— 15 = 285 units (exceeds total units, adjust to maximum possible, which is 180 units) Since the total work is completed in the given period, x = 0 days

      Practice Next
      ask-question