Question
'x' men can complete a work in 60 days. If there had
been 20 more men, the work would have been completed in 30 days. Find the value of 'x'.Solution
According to the question, the total amount of work is 60x units. Therefore: 60x=(x+20)Ă—30 60x=30x+600 30x=600 x = 600/30Â x = 20
The Reserve Bank of India (RBI) signed an agreement with Indonesia’s central bank to promote cross-border local currency transactions. This agreement ...
Which of the following best describes the discount factor used in capital investment decision-making ?
In the financial statements, contingent liability is ________
Which of the following RBI directions provides the legal authority for the issuance of the Master Direction on KYC?
 Where is the headquarter of SIDBI located?
The Ministry of MSME, Government of India and SIDBI set up a fund with a view to facilitate flow of credit to the MSE sector without the need for colla...
The ratio of change in the price of call option to the change in the price of the underlying stock is called:
As per section 44 of the Companies Act 2013, The shares or debenture or other interest of any member in a company is movable property transferab...
How much did HDFC Bank sell its stake in Protean eGov Technologies for?
Which of the following statements are not correct:
1.   Project Design and network analysis refers to detailed work plan to the project and i...