Question
A can complete a work in 12 days and B can complete the
same work in 18 days. They work together for 4 days, after which A leaves. In how many more days will B alone complete the remaining work?Solution
A's 1-day work = 1/12 B's 1-day work = 1/18 Together 1-day work = 1/12 + 1/18 = 3/36 + 2/36 = 5/36 Work done in 4 days = 20/36 = 5/9 Remaining work = 1 - 5/9 = 4/9 Time taken by B alone = (4/9) ÷ (1/18) = (4/9) × 18 = 8 days Hence, the correct answer is 8 days.
Name of Albania’s AI Cabinet Minister avatar?
Which of the following substance produces brisk effervescence when treated with baking-soda solution?
Algae often float on surface of water during day but sink during night due to:Â Â
Which organ controls reflex actions?
Kindly Study the following questions carefully and choose the right answer.
Which of the following is/are true with respect to Amoeba?
I...
The main function of centriole is:
Silicon is an example ofÂ
Which of the two temperature scales are same ?
 The site where complete digestion of carbohydrates, proteins and fats takes place is called
Which one of the following gases is supporter of combustion?