Question
A can complete a work in 12 days and B can complete the
same work in 18 days. They work together for 4 days, after which A leaves. In how many more days will B alone complete the remaining work?Solution
A's 1-day work = 1/12 B's 1-day work = 1/18 Together 1-day work = 1/12 + 1/18 = 3/36 + 2/36 = 5/36 Work done in 4 days = 20/36 = 5/9 Remaining work = 1 - 5/9 = 4/9 Time taken by B alone = (4/9) Γ· (1/18) = (4/9) Γ 18 = 8 days Hence, the correct answer is 8 days.
A paper is folded and cut as shown below. How will it appear when unfolded?
The sequence of folding a piece of paper and the manner in which the folded paper has been cut is shown in the following figures. How would this paper l...
The sequence of folding a piece of paper and the manner in Which the folded paper has cut is shown in the following figures. How would this paper look w...
A piece of paper is folded and cut as shown below in the question figure. How will it appear when unfolded?
In the question, assuming the given statements to be true, find which of the conclusion (s) among given two conclusions is /are definitely true and the...

A paper is folded and cut as shown in the following figures. How would this paper look when unfolded?
The sequence of folding a piece of paper and the manner in which the folded paper has been cut is shown in the following figures. How would this paper l...
- The sequence of folding a piece of paper and the manner in which, it is folded has been cut as shown in the following figure. How would this paper look whe...