Question
Kabir can build a fence in 16 days. Working together, Kabir and Arjun can finish it in 8 days. How long will Arjun take to build the fence alone?
More Time and work Questions
- ‘A’ can complete a work in 15 days and is 50% more efficient than ‘B’. ‘A’ and ‘B’ start working together and ‘A’ leaves after 8 days. The rest of the work...
- Bholu and Golu have teamed up to finish a task. On his own, Bholu can complete 5 units of work each day. Golu, when working solo, can finish the entire tas...
- Work Efficiency of Raghav and Vaibhav are in the ratio of 12:14. Both of them worked together and finished the work in 9 days. In how many days, the total ...
- A can finish a job in 20 days while B can finish same job in 30 days. A and B both worked for 5 days and C joins them. In next 3.5 days, all three have man...
- Rahul can complete a project in 50 days, while Karan can finish the same project in 75 days. Rahul starts working alone, and after 30 days, Karan joins him...
- A, B and C can complete a piece of work in 12 days, 15 days and 20 days respectively, if they work alone. They all start working together, but C leaves aft...
- If a group of 20 boys and 10 girls can finish a task in 50 days, and a team of 8 girls alone can complete the same task in 120 days, how long will it take ...
- Working alone, B can complete the work in 30 days. C is twice as efficient as B and A takes 20 days more than it takes C to complete the work. Working toge...
- P can do a piece of work in 12 days, Q can complete double the work in 20 days and R can do the work in 15 days. If all of them together earn Rs. 2500, the...
- A can complete a work in 15 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 80% of the work...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)