Question
When 24 men work for only 3 days, 5/6th of work remains unfinished. How much work will remain unfinished if 27 men work for only 2 days?
More Time and work Questions
- A work can be completed by ‘A’ and ‘B’, alone in 20 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- P can do a work in 20 days, Q in 30 days. They work together, but P leaves 5 days before completion. Find total time.
- A tank is filled by three pipes with uniform flow. The first two pipes operating simultaneously fill the tank in the same time during which the tank is fil...
- Ravi, Mohit and Sohan can complete a work in 24 days, 48 days and x days respectively. They started the work together and after 4 days, Ravi left the work....
- A and B together can finish a task in 35 days. If B is 40% more efficient than A, how many days will it take for B alone to complete the task?
- 'Zara' is capable of finishing a specific task in 60 days. On the other hand, 'Armaan' takes 40% more time than 'Zara' to complete the same task, while 'Ta...
- 25 men can complete a piece of work in 13 days. One man starts the work and after every day one more man joins the work and this continues till the work is...
- ‘A’ and ‘B’ can do a piece of work in 15 days and 18 days, respectively. They started working together but ‘A’ left after 5 days. Find the time taken by ‘B...
- X can do a piece of work in 33 days. He worked at it for 3 days and then Y finished it in 20 days. In how many days can X and Y together finish the work?
- A team of 12 men and 18 women can complete a construction project in 24 days. If 6 women alone can do the same project in 144 days, how many days will 48 m...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt