When 24 men work for only 3 days, 5/6th of work remains unfinished. How much work will remain unfinished if 27 men work for only 2 days?
More Time and work Questions
- In how many days can ‘Q’ alone complete the work? I. P, Q and R together can complete the work in 9`(3)/(13)` days. II. P and Q together can complete t...
- Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20% mo...
- Working in a shift of 5 hours 39 workers take 12 days to build a stretch of highway. In how many days will 30 workers working 6 hours a day, complete the w...
- 55 men can complete a piece of work in 12 days. 15 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remainin...
- 'A' can do 50% of work in 10 days, whereas 'B' can do 25% of the same work in 8 days. 'A' and 'B' started the work, but 'B' left the work 'n' days before c...
- A and B can complete a piece of work in 12 days and 15 days respectively. They start working together, but after 4 days, A leaves. In how many more days wi...
- Riya can do a piece of work in 30 days, and Mehul can do it in 45 days. Find the number of days Kabir will take to complete the job if he is 20% more effic...
- ‘P’ can complete 80% of a task in 32 days and ‘Q’ can do 60% of the task in 54 days. If ‘P’, ‘Q’, and ‘R’ all work together, they can complete the full tas...
- ‘A’ is 20% more efficient than ‘B’. ‘A’ and ‘B’ work together for 6 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 6 more days to finis...
- (y+40) boys can do a piece of work in (z-20) days. (y-5) boys can do the same piece of work in (z+20) days. If (y+30) boys can do the same piece of work in...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt