Question
When 24 men work for only 3 days, 5/6th of work remains
unfinished. How much work will remain unfinished if 27 men work for only 2 days?Solution
Work done by 24 men in 3 days = 24 × 3 =72 which is 1/6th of the total work So, total work = 6 x 72 = 432 Remaining work = 5/6 Work done by 27 men 2 days = 27 x 2 = 54 Required answer = (432 – 54)/432 = 7/8
Integrated Circuits have been introduced in which computer generation?
Which fraction bears the same ratio to 1/27 as 3/11 does to 5/9?
Under the provisions of the Industrial Disputes Act, 1947, right of legal representation before a Labour Court, or Industrial Tribunal or National Indu...
To whom does NABARD extend refinance assistance?
On 18th September, 2019, Shyam Ramsay died at the age of 67, he was known for which field?
With which of the following sports is Karun Chandhok associated?
Choose the incorrect statement about missile named as “Martyr Qassem Soleimani”.
______ book has been penned down by the author Devdutt Pattanaik?
As per Olympic rules, in the third game, badminton players change ends when a side scores _____ points
Which of the following statements is correct regarding Depreciation?Â
I. Depreciation is termed as loss of value of fixed assets due to wear and...