Question
A team of 32 men and 28 women can complete a task in 60
days. When an additional eight men join the team, they are able to finish (4/5) of the same task in 40 days. What is the amount of time needed for 84 women to complete 200% of the same task?Solution
ATQ, Let the efficiency of a man and a women be 'a' and 'b'Β units/day respectively Then, [(32a + 28b) Γ 60]/1 = [(40a + 28b) Γ 40]/(4/5) 192a + 168b = 200a + 140b (a/b) = (7/2) Total work = [((32 Γ 7) + (28 Γ 2)) Γ 60] = 16800 units hence required days = [(2 Γ 16800) /(84Γ2)]Β = 200 days
Under the Pradhan Mantri Kisan Samman Nidhi (PM-KISAN) scheme, the financial assistance provided to eligible farmer families is:
From the given options, select the one that CANNOT be listed among the long-run effects of ozone depletion.
Which of the following statement is correct about Constitution (105th Amendment) Act 2021?
I. President Droupadi Murmu has given her assent to th...
Which of the following statements is correct regarding Depreciation?Β
I. Depreciation is termed as loss of value of fixed assets due to wear and...
Who can make recommendations regarding the division of the net proceeds of taxes between the Union and the states?
The Indian Air Force was established on:
What was the amount allocated for agriculture in this year's budget by the finance ministry?
What is the primary aim of the Memorandum of Understanding (MoU) signed between the Indian Navy and M/s Uber?
GST was introduced as the ______ Amendment Act.
Which is the largest peninsular river in India?