Question

30 workers are laying a 6 km railway track. After 18 days, they finish 3/5 of the total work. To speed it up, 10 more workers are added. How many days will it take to lay the remaining track?

A 25 days Correct Answer Incorrect Answer
B 9 days Correct Answer Incorrect Answer
C 10 days Correct Answer Incorrect Answer
D 12 days Correct Answer Incorrect Answer

Solution

ATQ, Let the number of days to complete the remaining work be x. (30 × 18) / (3/5 × 6) = 40x / (2/5 × 6) (30 × 18) / (18/5) = 40x / (12/5) 150 = 40x / (12/5) 150 = (40x × 5) / 12 150 = (200x) / 12 150 × 12 = 200x 1800 = 200x x = 9 days

Practice Next
More Time and work Questions

Relevant for Exams:

ask-question