Question
'Sita' can complete some work alone in 20 days. 'Geeta'
is twice as efficient as 'Reeta' and three times as efficient as 'Sita'. If 'Sita' and 'Reeta' start working together, then after how many days should 'Geeta' replace them so that the work gets completed in exactly 8 days?Solution
Sita's rate = 1/20 Geeta = 3 Γ Sita β 3/20 Geeta = 2 Γ Reeta β Reeta = 3/40 Sita + Reeta = 1/20 + 3/40 = (2 + 3)/40 = 1/8 Let Geeta join after x days: Work by Sita & Reeta = x Γ 1/8 = x/8 Work by Geeta = (8 β x) Γ 3/20 Total work = 1: x/8 + (8 β x) Γ 3/20 = 1 β (β x + 48)/40 = 1 β x = 8 Hence, Geeta should replace them after 8 days (i.e., not needed at all)
60 men can complete a piece of work in 12 days. 12 men started the same work and worked for 10 days, and then joined by βxβ more men such that the r...
Worker A can build a wall alone in 30 days. When A and B work together, they can complete the wall in 16 days. If B starts building the wall alone and w...
A can finish a task in 32 days, while B can complete the same task 8 days sooner than A. If they together earn a total of Rs. 1050 for the job, how much...
A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 m...
Ratio of the work done by P, Q and R in one day is 5:4:8 respectively. They all together can complete the work in 40 days. Q and R worked on it for 20 d...
8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women w...
A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after βxβ days, after whic...
A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C...
Aβ and βBβ together can complete a work in 22 days while βAβ takes 33 days to complete the same work alone. If βCβ is 20% more efficient t...
P and Q can complete a piece of work individually in 12 days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work...