Question
‘A’ is 50% less productive compared to ‘B’, who is 20% more productive than ‘C’. Together, they can finish a task in 36 days. After ‘B’ and ‘C’ have worked on the task for 24 days, they stop. How long will it take for ‘A’ to finish the remaining work alone?
More Time and work Questions
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...
- P and Q individually can complete a work in 20 days and 30 days respectively. If the time taken by R alone to complete the work is 1.5 times the time taken...
- Karan, Arjun and Krunal alone can complete a work in 40, 60 and 48 days respectively. All of them started working together but after 3 days from start Kara...
- ‘F’ is 66.67% more efficient than ‘G’. ‘G’ worked alone for 10 days, and then ‘F’ completed the rest of the work. If the entire job was finished in 35 days...
- A work is done by A, B, C and D together. The percentage of work done by A, B C and D are in arithmetic progression (AP). The first, second, third and four...
- Alice can build one section of a wooden fence with a base length of 18 meter and a height of 25 meter in 18 days. Bob can construct 80% of one side of a wo...
- Person 'X' can finish a task in 40 days while 'Y' can do it in 50 days. How long will it take if both work together?
- 'A' and 'B' can do a piece of work together in 30 days. They worked together for 18 days, and then left the work. The remaining job was finished by 'C' alo...
- P and Q together can do a piece of work in 30 days, Q and R together can do it in 20 days. P starts the work and works on it for 5 days, then Q takes it up...
- Four boys and nine girls can complete a task in 24 days. Three boys and five girls can finish the same task in 36 days. How many days will it take for six ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt