Question
A takes twice as much time as B and thrice as much time
as C to finalize a task. Working together, they can complete the task in 8 days. The time (in days) taken by A, B and C, respectively, to complete the task isSolution
A            B            C Let time ATQ-                   6            3            2 Then Efficiency-               1            2            3 Total efficiency=1+2+3=+ Taken time to complete whole work = 8 days Total work =6×8=48unit A=48/1=48days B=48/2=24days C=48/3=16days
The H.M. and G.M. of a distribution are 8 and 10 respectively. Then the A.M. is
What does the Exchange Rate Pressure Index (ERPI) measure?
A producer received ₹ 6,000 when the price of a commodity was ₹ 60 per unit. The receipts increased to ₹ 8,400 when the price increased by ₹ 10....
Multicollinearity causesÂ
Classical economists argue that money is neutral because
The level of current inflation is 12% and inflation for the previous year was 6%. The strength of the effect of unemployment on the wages is 1.5. Calcul...
If bxy = 0.20 and rxy = 0.50, then byx is equal to:
In a futures contract, if the spot price at maturity is lower than the agreed futures price, the party with a 'Short Position' will:
The "Marshall-Lerner Condition" must be satisfied for a currency depreciation to:
Percentage of values that lie within a band around the mean in a normal distribution with a width of two standard deviations is approximately