Question

A takes twice as much time as B and thrice as much time as C to finalize a task. Working together, they can complete the task in 8 days. The time (in days) taken by A, B and C, respectively, to complete the task is

A 48,24,16
B 18,9,6 3.
C 36,18,12
D 72,36,24