Question
25 laborers working 7 hours daily can finish a road in
16 days. If 35 laborers work 8 hours each day, how many days are needed?Solution
ATQ,
Let the efficiency of a laborer = 'x' units/hour
Total work = 25 × x × 7 × 16 = 2800x units
Number of days = 2800x ÷ (35 × x × 8)= 2800x ÷ 280x = 10 days
In whose favour is the Doctrine of Indoor Management?
When was the Government e-Marketplace (GeM) launched in India?
The GST on used car sales is ____ as per the 55th GST council meeting decisions taken in December 2024.
Which of the following statements is INCORRECT?
What is the minimum solvency ratio required by IRDAI for general insurers in India?
For intra-State sales, the GST is divided between the Centre and the State in the ratio?
An insurer has Net Profit before tax ₹50 lakh, depreciation ₹8 lakh, increase in trade payables ₹5 lakh, decrease in inventory ₹2 lakh, and gain...
Which of the following is not an objective of management accounting?
Which of the following transactions is revenue expenditure?
GST applies to all goods and services EXCEPT: