Question
25 laborers working 7 hours daily can finish a road in
16 days. If 35 laborers work 8 hours each day, how many days are needed?Solution
ATQ,
Let the efficiency of a laborer = 'x' units/hour
Total work = 25 × x × 7 × 16 = 2800x units
Number of days = 2800x ÷ (35 × x × 8)= 2800x ÷ 280x = 10 days
Shore temple of Mamallapuram was built by:
Which of the following vitamins includes cobalt as an essential component?
Who are eligible for the PM Shram Yogi Maan-dhan Yojana?
Gangu bai Hangal and Prabha Atre were exponents of the ___________ Gharana.
How many aircraft took part in Republic Day fly past of 2022 in India?Â
Ustad Binda Khan is associated with which of the following instruments?Â
Exit for NPS: In case the total corpus in the account is less than or equal to _________ as on the Date of Death of the Subscriber (Government sector), ...
SHREYAS National Fellowship Scheme has benefitted more than 21,000 SC Students in higher education, when was it launched?
The walls and ceiling of an auditorium are covered with fibrous material, such as glass fibre, to
As of March 2024, who among the following is the Chairperson of the National Green Tribunal?