      25 laborers working 7 hours daily can finish a road in

      16 days. If 35 laborers work 8 hours each day, how many days are needed?
      A 10 days Correct Answer Incorrect Answer
      B 12 days Correct Answer Incorrect Answer
      C 14 days Correct Answer Incorrect Answer
      D 28 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the efficiency of a laborer = 'x' units/hour

      Total work = 25 Ă— x Ă— 7 Ă— 16 = 2800x units

      Number of days = 2800x Ă· (35 Ă— x Ă— 8)= 2800x Ă· 280x = 10 days