Get Started with ixamBee
Start learning 50% faster. Sign in now
Time taken by A to complete the work = 32 days Time taken by B to complete to the work = 32 – 12 = 20 days Time taken by C to complete the work = 12/0.25 = 48 days Let the total work = 480 units Efficiency of A = 480/32 = 15 units/day Efficiency of B = 480/20 = 24 units/day Efficiency of C = 480/48 = 10 units/day Therefore, 1 days work of (A + B + C) = 15 + 24 + 10 = 49 units Therefore, required time taken = 0.6125 × 480/49 = 6 days
What is the integral value of sin mx
Consider the below data: