Question
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alone in 3x days, then find the value of
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alone in 3x days, then find the value of
x.
More Time and work Questions
- ‘A’ is 80% more efficient than ‘B’. ‘A’ and ‘B’ work together for 5 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 10 more days to fini...
- A can finish a work in 18 days and B can finish it in 24 days. They work together for 6 days, then A leaves. In how many more days will B finish the remain...
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
- Aaru Swati and Rajni can finish a work in 4 days if they work together. However, Aaru alone will take 9 days to complete the work, and Swati alone will com...
- 'A' alone can do some work in 12 days. 'B' is 50% more efficient than 'A'. 'A' worked alone for 3 days and left. How much time (in days) does 'B' need to f...
- 40 men can complete a piece of work in 24 days. All of them started the work together, after 6 days how much more men will be required to complete the same...
- ‘A’ alone can complete a work in 10 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 3 days, then the remaining work...
- Three Typists Axe, Wye and Zed working together 3 hours per day and can type 720 pages in 12 days. In a day Wye types as many pages more than Axe as Zed ty...
- Time taken by A and B together to complete a work is 1 day less than the time taken by B alone to complete the same work. With his half efficiency B can co...
- Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish the ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)