Question
P and Q can do a piece of work in 32 and 40 days
respectively. They began to work together but P leaves after sometimes and Q completed remaining work in 16 days. After how many days did P leaves (in days)?Solution
Let P worked for x days According to question ⇒ `x/32+(x+16)/40` = 1 ⇒ `(5x+4(x+16))/160` = 1 ⇒ 5 x + 4x + 64 = 160 ⇒ 9x = 160 – 64 = 96 ⇒ `x=96/9=32/3 days P left the work after 32/3 days. Alternate Method; P Q 32 40 LCM = 160 units 5 : 4 For last 16 days, Q alone completed = 4 x 16 = 64 units So remaining is done by both = (160 -64)/(5+4) = 96/9 = 32/3 days Hence P left after 32/3 days.
√3598 × √(230 ) ÷ √102= ?
Simplify the following expressions and choose the correct option.
45% of 640 + (2/5 of 350) = ?
√225 + 27 × 10 + ? = 320
32 X 25 ÷ 4 + 12 of 30 = ? X 5 - 30Â
1440 ÷ 12 + 540 ÷ √36 + ? = 180 * 3
4567.89 - 567.89 - 678.89 = ?
- What will come in place of the question mark (?) in the following questions?
18×4+96÷8=? ((12+12+12+12)÷4)/((8+8+8+8+8+8)÷16) = ?
9999² + 1111² =?
- What will come in the place of question mark (?) in the given expression?
(120 - ?) ÷ 2 + 35 = 86 - 11