📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    Worker ‘P’ can finish a task in 54 days, which is 18

    days quicker than worker ‘Q’. If they take turns daily starting with ‘P’, find the total time (in days) to complete the task.
    A 72.5 days Correct Answer Incorrect Answer
    B 44.5 days Correct Answer Incorrect Answer
    C 61.5 days Correct Answer Incorrect Answer
    D 37.5 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Time taken by 'Q' = 54 + 18 = 72 days Let total work be 216 units (LCM of 54 and 72) Efficiency of 'P' = 216 ÷ 54 = 4 units/day Efficiency of 'Q' = 216 ÷ 72 = 3 units/day Work in 2 days = 4 + 3 = 7 units Work in 60 days = 7 × 30 = 210 units Remaining work = 216 - 210 = 6 units Time by 'P' to finish remaining = 6 ÷ 4 = 1.5 days Hence, final Answer: 60 + 1.5 = 61.5 days

    Practice Next

    Relevant for Exams:

    ask-question