Question
Three workers P1, P2 and P3 got work from the contractor. In 30 days, ‘P1’ completed 30% of work. ‘P2’ is 20% less efficient than ‘P1’ but takes 5 days less than ‘P3’ to complete the work alone. Find the time taken by all three together to complete 33.4% of work.
More Time and work Questions
- Sita is 50% more efficient than Simran. Working together, they finish the work in 24 days. How long will Sita take to complete the work alone?
- A can complete 5/6 of a work in 15 days and B can complete 2/3 of work in 8 days. In how many days both A and B together can complete the work?
- Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the sa...
- 'A' can do 50% of work in 10 days, whereas 'B' can do 25% of the same work in 8 days. 'A' and 'B' started the work, but 'B' left the work 'n' days before c...
- A certain number of men, represented as 'm', can finish a task in 40 days. However, if there were 15 additional men, the same task would be completed in 25...
- A can complete a piece of work in 16 days and B can complete it in 24 days. They work together for 4 days and then B leaves. In how many total days is the ...
- X and Y alone can complete a work in 10 and 40 days, respectively. 50% of the work is completed by Z in 20t days, and the remaining work is completed by X ...
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- 25 men can finish a work in 8 days by working 9 hours a day. How many more men are needed to finish the work in 10 days by working 6 hours a day?
- (x + 6) workers complete 40% of a job in 8 days by working 5 hours/day. The remaining work is done by (x + 2) workers in 16 days working 5 hours/day. Find ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt