Question
Ashish and Anil can do a piece of work in 15 days and 20
days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 15 and 20) = 60 units Efficiency of Anil = 60/20 = 3 units/day Remaining work = 60 x 0.4 = 24 units Time taken by Anil to complete the remaining work = 24/3 = 8 days
Select the figure from among the given options that can replace the question mark (?) in the following series.
Seven boxes K, L, M, S, T, U and V are kept one over the other but not necessarily in the same order. No box is kept above T. Only three boxes are kept ...
A series is given with one term missing. Select the correct alternative from the given ones that will complete the series.
LRMC, OUPF, RXSL, UAVL,?
Two positions of a cube are shown. What will come opposite to the face showing ‘@’?
In a certain code language, 'EATING' is coded as "ELGRYC'. What is the code for 'COFFEE' in that code language?Â
Study the following figure and answer the question that follows.
Find out the correct alternative that when filled in the blanks in the same sequence will make the series logically complete.
ZA_J B_BK DAB_ _ ABM HA_N
Select the wrong term in the given alpha-numeric series.
L11, O22, R44, U44, X55
Select the set in which the numbers are related in the same way as are the numbers of the following sets. (NOTE: Operations should be performed on the w...
P started a work by investing ₹6,000. After 6 months Q joined with an amount of ₹14,000. After 1 year R joined with ₹12,000. After two years of wo...