Question
Ashish and Anil can do a piece of work in 15 days and 20
days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 15 and 20) = 60 units Efficiency of Anil = 60/20 = 3 units/day Remaining work = 60 x 0.4 = 24 units Time taken by Anil to complete the remaining work = 24/3 = 8 days
In the context of a BoP Deficit, which of the following statements accurately describes the role of Accommodating Transactions?Â
What growth rate did the IMF project for India for 2024-25?
1.   Given the following, what is the amount of Capital?
Assets: Premises 20,000; Inventory 8,500; Cash 100.
Liabilities: Trade Payab...
Which of the following is not a fundamental accounting assumption as per AS-1?
A company purchases raw material from a US-based supplier for USD 10,000 on January 1, 20X1, when the exchange rate is ₹87/USD. The payment remains...
What is the tenor of the Sovereign Gold Bond (SGB) bond, and when is early encashment/redemption allowed?
What percentage of UPI transaction volume growth was reported year-on-year in July 2024?
Where are ethical standards typically based?
A company reported a Net Profit of ₹5,00,000. During the year, Depreciation was ₹80,000, Gain on Sale of Machinery was ₹20,000, and Trade Receivab...
As per SEBI regulations, Alternate investment Funds (AIF) have been allowed to invest in ______