Question
Ashish and Anil can do a piece of work in 15 days and 20 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the remaining work.
More Time and work Questions
- X men can complete the piece of work in 50 days and (X + 51) men can complete the same work in 30 days less than that of days taken by X men. Find the valu...
- Working together, Amit and Pawan can finish a task in 22.5 days, and Pawan and Chirag can complete 60% of the same task in 14.4 days. Given that Amit is 12...
- (x) men can do some work in 42 days. If 10 more men added then the work would have been completed in 30 days, then in how many days (x+45) men can do the s...
- A, B, and C together wrap up a task in 14 days. B and C together can finish it in (280/18) days, and C alone completes half in 14 days. Find the ratio of t...
- P, Q and R can do some work in 11 days, 20 days and 55 days respectively. In how many days can the work be done, if P gets the assistance of Q and R on alt...
- A alone can finish a piece of work in 10 days, and B alone can finish it in 15 days. In how many days can they finish it together?
- The time taken by ‘A’ to build a wall alone is 40% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
- A and B can complete a work together in 25 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
- Komal and Seema individually can complete a task in ‘4a’ hours and ‘6a’ hours respectively. If they together can complete half of the work in 6 hours, then...
- A and B together can complete a task in 12 days, while B and C together can complete the same task in 15 days. A and C together take 20 days to finish it. ...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt