      Ashish and Anil can do a piece of work in 15 days and 20

      days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the remaining work.
      A 10.5 days Correct Answer Incorrect Answer
      B 8 days Correct Answer Incorrect Answer
      C 9 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      Let the total work be (LCM of 15 and 20) = 60 units Efficiency of Anil = 60/20 = 3 units/day Remaining work = 60 x 0.4 = 24 units Time taken by Anil to complete the remaining work = 24/3 = 8 days