Question
Ashish and Anil can do a piece of work in 15 days and 20
days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 15 and 20) = 60 units Efficiency of Anil = 60/20 = 3 units/day Remaining work = 60 x 0.4 = 24 units Time taken by Anil to complete the remaining work = 24/3 = 8 days
Software whose source code is available to users for modification and improvement is known as _______. Â
Who was the first scientist to be awarded two Nobel Prizes?
For which genre of writing is the Booker Prize awarded?
Dr. Sandhaya Puricha received the Lacchu Maharaj Award for her contributions to which dance form?
Why is water commonly used in car radiators?
Who is elected as the chairman of the Indian Farmers Fertiliser Cooperative (IFFCO)?
Where is the Headquarters of the International Labour Organisation (ILO)?
What reports all program errors along with the line numbers? Â
Who was the first recipient of the Jnanpith Award.
Where is the Sultan Azlan Shah Cup held every year ?