Question
Ashish and Anil can do a piece of work in 15 days and 20
days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 15 and 20) = 60 units Efficiency of Anil = 60/20 = 3 units/day Remaining work = 60 x 0.4 = 24 units Time taken by Anil to complete the remaining work = 24/3 = 8 days
State Bank of India has set up_____Â Hubs at the Top 21 district centres across the country to provide quick and efficient transaction banking solution...
Which initiative was launched by the Union Government to address the maritime trade deficit of $50 billion?
In December 2021, IIT-_______ signed an MoU with the Indian Air Force (IAF) to accelerate IAF’s indigenisation efforts for achieving self-reliance . ...
What is the duration of the proposed Golden Visa under Vietnam's new visa scheme?
- What was Syed Abid Ali’s best bowling figure in Test cricket?
The Government of India’s Centres of Excellence for Green Hydrogen research will focus on which of the following activities?
What was the significant achievement of Agnikul's Agnibaan launch vehicle?
Bhupendrabhai Patel will release Gujarat’s First “District Good Governance Index”, of Gujarat, prepared by Department of Administrative Reforms & ...
How much fine has been imposed by the Reserve Bank of India on Punjab and Sind Bank for non-compliance with certain directions on 'Loans and Advances St...
What is the annual budget allocation for PM Dhan-Dhaanya Krishi Yojana (PMDDKY)?