Question

    P can do a piece of work in 20 days, Q can do the same

    piece of work in 24 days while R can do it in 30 days. They started working together but after 4 days ‘P’ left the work and the remaining work was completed by Q and R together. Find in how many days will the work be completed?
    A 4(2/3) days Correct Answer Incorrect Answer
    B 6(1/2) days Correct Answer Incorrect Answer
    C 6(2/3) days Correct Answer Incorrect Answer
    D 6(2/5) days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    P – 20 days P – 6 unit Q – 24 days LCM = 120 Q – 5 unit R – 30 days R – 4 unit Work of all 3 per day is (6 + 5 + 4) – 15 units All worked for 4 days. So, 4 days work is 4 × 15 = 60 units Remaining work = 120 – 60 = 60 units That work done by Q and R their per day unit = (5 + 4) = 9 unit Remaining work done by Q and R is `60/9` days =`6 2/3` days

    Practice Next