Question
'J', 'K' and 'L' can complete a task alone in 42, 21, and
14 days respectively. If 'K' and 'L' work together for 'x' days and leave, then 'J' completes the rest in 7 days. What is the value of 'x'?Solution
ATQ,
Let the total work = L.C.M of 42, 21, and 14 = 84 units
Efficiency of 'J' = 84 ÷ 42 = 2 units/day
Efficiency of 'K' = 84 ÷ 21 = 4 units/day
Efficiency of 'L' = 84 ÷ 14 = 6 units/day
Work done by 'J' in 7 days = 2 × 7 = 14 units
Work done by 'K' and 'L' in 'x' days = 84 - 14 = 70 units
So, x = 70 ÷ (4 + 6) = 7
What is another term commonly used to refer to the outermost layer of an animal cell, which is selectively permeable and composed mainly of lipids and p...
When total product remains constant, the marginal Product will be?
The word Crown cleaning related to which of the following crop?
_____ are the compounds used to improve the nutritional value of the basal feeds so as to take care of any deficiency.
Income elasticity of demand for giffen goods is
In a certain code language TROUBLE is written as GNDWQTV. How would the word TEACHER be written in the same code language?
Which one is calculated in Quintal per ha-
Iso - revenue line represents the
Who formulated the theory of natural selection and published it in the book "On the Origin of Species" in 1859?
To create informative content and engagement material, along with simple messaging asking citizens to be aware, be cognizant and be receptive to SNF (s...