Question
'J', 'K' and 'L' can complete a task alone in 42, 21, and
14 days respectively. If 'K' and 'L' work together for 'x' days and leave, then 'J' completes the rest in 7 days. What is the value of 'x'?Solution
ATQ,
Let the total work = L.C.M of 42, 21, and 14 = 84 units
Efficiency of 'J' = 84 ÷ 42 = 2 units/day
Efficiency of 'K' = 84 ÷ 21 = 4 units/day
Efficiency of 'L' = 84 ÷ 14 = 6 units/day
Work done by 'J' in 7 days = 2 × 7 = 14 units
Work done by 'K' and 'L' in 'x' days = 84 - 14 = 70 units
So, x = 70 ÷ (4 + 6) = 7
If 50 percent of the families in a certain city subscribe to the morning newspaper, 65 percent of the families subscribe to the afternoon newspaper and ...
The 'Special Drawing Right (SDR)' is an international reserve asset created by:
What is the primary theme of India’s Union Budget 2024-25?"
The Mundell-Fleming framework studies (A) _____ , (B) _________ economies in a world with (C) _____ financial markets and (D) _____ capital mobility
Which among the following are the recommendations of the Urjit Patel Committee report on monetary policy?
I. Curtailment of the fiscal deficit.
Under the Bretton wood system, the long-term development assistance was to be provided by
-
IBRD
...
-
If rxy = 0.75, then ryx will be:

When a firm operates with excess capacity