      Question

      'Ravi', 'Sohan', and 'Karan' can individually finish a task

      in 45, 30, and 60 days, respectively. Sohan and Karan work together for β€˜x’ days and then leave. Ravi completes the remaining work in 9 days. What is the value of β€˜x’?
      A 10 Correct Answer Incorrect Answer
      B 14 Correct Answer Incorrect Answer
      C 18 Correct Answer Incorrect Answer
      D 16 Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the total work = L.C.M of 45, 30, and 60 = 180 units

      Efficiency of Ravi = 180 Γ· 45 = 4 units/day

      Efficiency of Sohan = 180 Γ· 30 = 6 units/day

      Efficiency of Karan = 180 Γ· 60 = 3 units/day

      Work done by Ravi in 9 days = 4 Γ— 9 = 36 units

      Work done by Sohan and Karan = 180 - 36 = 144 units

      So, x = 144 Γ· (6 + 3) = 144 Γ· 9 = 16 days