Question
'Ravi', 'Sohan', and 'Karan' can individually finish a task in 45, 30, and 60 days, respectively. Sohan and Karan work together for ‘x’ days and then leave. Ravi completes the remaining work in 9 days. What is the value of ‘x’?
More Time and work Questions
- Working 10 hours a day, Jagan can complete a work in 12 days while working 8 hours a day, Magan can complete the same work in 9 days. If Jagan and Magan wo...
- (x + 3) workers complete 50% of work in 4 days at 5 hours/day. (x + 1) workers finish the rest in 5 days at 6 hours/day. Find x.
- 8 men working 6 hours a day can complete a piece of work in 6 days. If efficiency of each woman is 20% more than that of each man, then how many women work...
- 'B' can complete a task in 15 days, and when 'A' and 'B' collaborate, they can finish the same task in 8 days. 'A' initiated the work alone and worked for ...
- A and B together can complete a job in 2 days. A alone takes x + 6 days to complete the job, while B alone takes x + 24 days to complete the same job. 1.W...
- A and B can complete a job together in 30 days; B and C can complete the same job together in 25 days, while C and A can complete the same job together in ...
- A completes 1/3 of a task in 4 days, while B finishes the remaining work in 8 days. If B is 25% less efficient than C, how many days will A, B, and C toget...
- A and B together can complete a work in 20 days. After working together for 8 days, B leaves, and A completes the remaining work in 16 more days. In how ma...
- A man, a woman and a boy can do a work in 4, 8, 16 days respectively. How many boys were required with 1 man and 1 woman to complete the same work in 1/2 d...
- A can do 1/4th of a work in 15 days, B can do the 25% of the work in 20 days & C can do 1/5th of the work in 15 days. Who will complete the work first?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)