Question

Time taken by 18 men working 8 hours a day to complete a work is 25 days whereas time taken by 30 women working 6 hours a day to complete the work is 30 days. Find the time taken by 10 men and 15 women working together 9 hours a day to complete the work.

A 15 days
B 18 days
C 20 days
D 24 days
E 30 days