πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A alone can finish a piece of work in 12 days and B

      alone in 18 days. They work together for 4 days, then B leaves and C joins A. A and C together finish the remaining work in 3 more days. In how many days can C alone finish the whole work?
      A 108/7 days Correct Answer Incorrect Answer
      B 100/7 days Correct Answer Incorrect Answer
      C 117/8 days Correct Answer Incorrect Answer
      D 125/7 days Correct Answer Incorrect Answer

      Solution

      Let total work = LCM(12, 18) = 36 units. A’s rate = 36/12 = 3 units/day B’s rate = 36/18 = 2 units/day Together (A + B) rate = 3 + 2 = 5 units/day. Work done in 4 days = 5 Γ— 4 = 20 units. Remaining work = 36 βˆ’ 20 = 16 units. Now A and C together finish 16 units in 3 days. So (A + C) rate = 16/3 units/day. A’s rate = 3 units/day, so C’s rate = (A + C) βˆ’ A = 16/3 βˆ’ 3 = 16/3 βˆ’ 9/3 = 7/3 units/day. Time taken by C alone = Total work / C’s rate = 36 Γ· (7/3) = 36 Γ— 3/7 = 108/7 days

      Practice Next
      More Time and work Questions
      ask-question