Question
βAβ and βBβ can do a piece of work in 20 days
and 40 days, respectively. If they started the work together and worked on it for 6 days, then find the time taken by βBβ alone to complete the remaining work.Solution
Let total amount of work be 40 unitsΒ Efficiency of βAβ = 40/20 = 2 units/day Efficiency of βBβ = 40/40 = 1 units/day Amount of work done by βAβ and βBβ together in 6 days = (2 + 1) Γ 6 = 18 units Time taken by B to complete remaining work = (40 β 18)/1 = 22 days
√3598 × √(230 ) ÷ √102= ?
15% of 2400 + (β 484 β β 256) = ?
(13)2Β - 3127 Γ· 59 = ? x 4
6269 + 0.25 × 444 + 0.8 × 200 = ? × 15
...(53 + 480 Γ· 4)% of 20 = ?% of 70
Find the simplified value of the following expression:
62 + 122 Γ 5 - {272 + 162 - 422}
(15 Γ 225) Γ· (45 Γ 5) + 480 = ? + 25% of 1240
β [? x 11 + (β 1296)] = 16
11 Γ 25 + 12 Γ 15 + 14 Γ 20 + 15 = ?