Question
32 workers can complete a task in 18 days. They all
started together, but after how many days should 12 workers quit so that the task gets completed in 27 days?Solution
ATQ,
Let the efficiency of each worker be 'm' units/day Total work = 32 × 18 × m = 576m units Let after x days, 12 workers quit According to the question: 32 × m × x + 20 × m × (27 − x) = 576m → 32mx + 540m − 20mx = 576m → 12mx = 36m → x = 36 ÷ 12 = 3 So, after 3 days the 12 workers should quit.
When is the International Day for the Preservation of the Ozone Layer observed?
___________ will sell 6% stake in SBI Mutual Funds which is a joint venture between State Bank of India and France’s Amundi Asset management.
Which state government recently declared desi (indigenous) cows as ‘Rajyamata-Gomata’?
 Who is the author of the biography titled "Vajpayee: The Ascent of the Hindu Right 1924-77," which captures the early years of late Prime Minister Ata...
Which of the following bank had been recently penalized by RBI to an amount of three crore
The Pradhan Mantri Vaya Vandana Yojana (PMVVY) provides social security to senior citizens. Which of the following best describes the scheme's purpose?
The town of Sanchi, famous for the Sanchi stupa is located in?Â
Which of the following firm launched world’s 1st GMS based Cowpea Hybrids?
Madhav National Park is situated in which of the following state?
In which state of India is Jharsuguda Airport located?