Question
32 workers can complete a task in 18 days. They all
started together, but after how many days should 12 workers quit so that the task gets completed in 27 days?Solution
ATQ,
Let the efficiency of each worker be 'm' units/day Total work = 32 Γ 18 Γ m = 576m units Let after x days, 12 workers quit According to the question: 32 Γ m Γ x + 20 Γ m Γ (27 β x) = 576m β 32mx + 540m β 20mx = 576m β 12mx = 36m β x = 36 Γ· 12 = 3 So, after 3 days the 12 workers should quit.
Where is the magnetic force of a bar magnet the strongest?
A pulse of light duration 10-5 s is absorbed fully by a little object initially at rest. If the power of this pulse is 45 Γ 10-3...
Self-inductance of a long solenoid is directly proportional to:
Which law explains why it is difficult to hammer a nail into a freely suspended wooden frame?
A meter stick moves along its length with a certain speed. The apparent length of the moving meter stick as measured by a stationary observer on the gr...
The weight (W) of a body is derived from which formula?
The time period of a secondβs pendulum is β
Cryogenics is the branch of physics that deals with what?
A galvanometer coil has a resistance of 14 Ξ© and the metre shows full scale deflection for a current of 4 mA. How will you convert the metre into a vo...
What type of radiation is produced by a hot object emitting energy?Β Β