Question
28 men can complete a work in 20 days. 40 women can
complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more women join them. How many days will they now take to complete the remaining work.Solution
Total work done by 28 men and 40 women is equal Therefore, efficiency of men and women 28 Γ M Γ 20 = 40 Γ W Γ 28 M : W = 2 : 1 Let Total work = 28 Γ 2 Γ 20 = 1120 unit Work done by 20 men and 12 women in 16 days = (20 Γ 2 + 12 Γ 1) Γ 16 =Β 832 unit Remaining work = 1120 β 832 = 288 unit Total Efficiency (inclusive of 20 women) = 52 + (20 Γ 1) = 72 Remaining work done in = 288/72 = 4 days
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
βXβ and βYβ can do a task together in 15 days. If βXβ alone takes 25 days to complete it, then how much time will βYβ take to finish the...
βPβ and βQβ can complete a task together in 24 days. If βPβ alone can do it in 40 days, find the number of days βQβ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?