Question
28 men can complete a work in 20 days. 40 women can
complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more women join them. How many days will they now take to complete the remaining work.Solution
Total work done by 28 men and 40 women is equal Therefore, efficiency of men and women 28 × M × 20 = 40 × W × 28 M : W = 2 : 1 Let Total work = 28 × 2 × 20 = 1120 unit Work done by 20 men and 12 women in 16 days = (20 × 2 + 12 × 1) × 16 = 832 unit Remaining work = 1120 – 832 = 288 unit Total Efficiency (inclusive of 20 women) = 52 + (20 × 1) = 72 Remaining work done in = 288/72 = 4 days
Several tumultuous years, was marked by a complex and multifaceted series of events A. transformations that resulted in the overthrow of the B...
A) Morocco is a beautiful place to visit.
B) There are many Moroccan Folk stories that are still told throughout Morocco today.
C) Travell...
Rearrange the following sentences in the proper sequence to form a meaningful paragraph and then answer the questions given below.
A. Carefully...
1. Anita persuaded the women to start working in the food-for-work programme started by an NGO, and for the children she organised sports events.
Which of the following is the first sentence of the passage?
I. The recent shift (A) in e-commerce platforms has reshaped (B) consumer behavior and shopping trends, leading to a significant surge (C) in the retai...
     I.       The Reserve Bank of India (RBI) invest A. a central role in monetary B. policy and banking innova...
- In the questions given below, a sentence has been divided into four fragments (A), (B), (C) and (D) and is arranged (not necessarily in the correct order)....
- In the questions given below, a sentence has been divided into four fragments (A), (B), (C) and (D) and is arranged (not necessarily in the correct order)....
- Below are given a few sentences with their parts jumbled in a random order. Below the sentences are given possible rearrangements of the parts. You need to...